Project Milestone |
Estimated Timeframe |
|
|
Prepare EA Terms of Reference |
2005 |
4 |
|
Submit EA Terms of Reference to Minister for Approval |
December 2005 |
4 |
|
EA Terms of Reference Approved |
March 2006 |
4 |
|
Initiate EA Study |
March 2006 |
4 |
|
Evaluate “Alternatives to” the Undertaking (i.e., Technologies) |
2006 |
4 |
|
Select Preferred Approach to Manage Residual Wastes |
2006 |
4 |
|
Evaluate “Alternative Methods” of Carrying Out the Undertaking (i.e., Siting) |
Late 2006 - End 2007 |
4 |
|
Selection of Preferred Durham/York Site |
End of 2007
|
4 |
|
RFP to Identify a Preferred Technology and Vendor |
Early 2008 |
|
|
Selection of Preferred Durham/York Technology Vendor |
Mid 2008
|
|
|
Complete Site Specific Studies to Confirm Suitability and Documentation to Support Approvals |
2008 |
|
|
Submit EAA Approval Documentation to Minister for Approval |
Late 2008 |
|
|
EA Review and Approval by Minister |
2009 |
|
|
Implementation of Undertaking |
Mid 2009 to 2011 |
|
|